How long does a bathroom renovation take, and which waits are fixed

A bathroom renovation runs on two kinds of wait. The products set some, such as the membrane's cure before a flood test. Calendars set the rest, such as a permit review when plumbing moves.

Published
Reading time
6 min read
Written by
Sonce Homes
Rendering of a freestanding soaking tub beneath a window on a cream and blue patterned tile floor.
Illustrative image

How long does a bathroom renovation take?

How long a bathroom renovation takes comes down to two kinds of wait. The products set some: Schluter recommends at least 24 hours after its shower membrane is set before the flood test starts. [Schluter Systems] Calendars set the rest, such as Newmarket's permit review of about 10 to 15 working days when plumbing moves. [Town of Newmarket]

A refit that keeps every fixture on its existing drain often does without a permit, which takes that review off the calendar. We found no official or manufacturer source that puts the whole job in weeks, so there is no total here. If a contractor quotes you one, ask which of the waits below it allows for.

Planning, a custom vanity and a permit if plumbing moves

Planning and design happen while the bathroom still works. Settle the layout first: where each fixture goes, tub or shower or both, and how much storage the room needs. Then choose the tile, vanity and fixture finishes together.

Ordering is different for two items in a bathroom. A custom vanity is built to the exact width of its wall, so confirm that width with whoever builds it before the order goes in. Shower glass cannot be ordered at this stage at all, because it is measured once the tile is set.

If a fixture moves, a permit question comes with it. Newmarket's building page lists plumbing alterations and adding or removing walls as permit work, while floor and ceiling finishes and painting typically need none. [Town of Newmarket] Once an application is complete, the Town needs about 10 to 15 working days to review it. [Town of Newmarket] It adds that the more complete the application, the quicker the review, so send everything it asks for the first time. [Town of Newmarket]

How long does a powder room take compared with a full bathroom?

A powder room is the shorter job because it has no shower. The membrane wait, the flood test and the days before a first shower all drop out, though its floor tile still waits on the thin-set and then on the grout.

A full bathroom or ensuite with a tiled shower has every wait in the table further down. A larger or custom bath adds tile to set and fittings to install rather than new kinds of wait: the cure times stay the same, and the work between them takes longer.

Demolition and rough-in: the walls stay open for the inspectors

Demolition comes first. The old tile and board come off, and the framing behind them is checked for water damage before anything new goes on. Then the plumbing is set where the new fixtures need it, and the wiring and boxes go in.

Almost all electrical work in Ontario needs a notification of work filed with the Electrical Safety Authority before it starts, and whoever does the work files it. [Electrical Safety Authority] ESA's rough-in inspection comes once the branch circuit wiring and outlet boxes are in, and before insulation, vapour barrier or drywall hides them, so the walls stay open until it passes. [Electrical Safety Authority]

A job with a building permit has the Town's inspections as well. In Newmarket they depend on the work and are listed on the reviewed plans under Mandatory Inspections. [Town of Newmarket] Each one needs two days' notice, and inspections are booked Monday to Friday, 8:30 a.m. to 4:30 p.m. [Town of Newmarket] Ask for the visit two days before the rough-in will be ready, not on the day it is, or the open walls sit through the notice period.

Why do waterproofing and tile take so long?

Each layer of a tiled shower sits on the one under it, so these waits cannot overlap. Every figure here is one named product's own, and another brand's data sheet can say something different.

After the rough-in, the walls get new board and a waterproofing membrane in the wet areas. Schluter recommends waiting at least 24 hours after setting its KERDI membrane before starting a water test, and longer when the room is much colder than normal. [Schluter Systems] The test plugs the drain, fills the base and marks the water level, then leaves it for a set time. [Schluter Systems]

Tile follows the test. MAPEI's Ultraflex 2 thin-set lists its own time before grouting and says that time varies with jobsite conditions. [MAPEI Ultraflex 2] MAPEI's Ultracolor Plus FA grout needs longer to cure when the air is below 16°C (60°F) or the relative humidity is above 70%. [MAPEI Ultracolor Plus FA]

WaitHow longWhose figure
Membrane set, then water test startsAt least 24 hoursSchluter KERDI [Schluter Systems]
Water test24 hours is typicalSchluter shower system [Schluter Systems]
Thin-set to grout16 to 24 hoursMAPEI Ultraflex 2 [MAPEI Ultraflex 2]
Tile protected from heavy traffic7 daysMAPEI Ultraflex 2 [MAPEI Ultraflex 2]
Grouted floor kept free of foot trafficAt least 3 hoursMAPEI Ultracolor Plus FA [MAPEI Ultracolor Plus FA]
Grout cured before regular cleaningAt least 24 hoursMAPEI Ultracolor Plus FA [MAPEI Ultracolor Plus FA]
First shower, cement-based grout3 days minimumMAPEI Ultracolor Plus FA [MAPEI Ultracolor Plus FA]

Fixtures, vanity and glass: the last stretch

Once the tile is grouted, the vanity, toilet, taps and lights go in, and the shower glass comes last of all. Glass and final finishing are the last wait before the room is back in use.

The electrical side closes with its own visit. ESA asks for the final inspection as soon as possible after the installation is complete, which means receptacles, switches, cover plates and light fixtures are in place. [Electrical Safety Authority] Electrical inspections take place from 8:00 a.m. to 4:00 p.m., Monday to Friday, except statutory holidays. [Electrical Safety Authority]

What makes a bathroom renovation take longer?

The delays that belong to a bathroom come from the wet areas, and they are tied to the waits in the table above.

A failed flood test is the first. The test is a check done on a shower before tile is set, and a shower that leaks does not pass. [Schluter Systems] The leak gets fixed before any tile goes on, which is the point of testing first, and the tile crew waits until it is.

Cold or damp air is the second. Schluter says to wait longer than 24 hours before water testing when the room is much colder than normal. [Schluter Systems] MAPEI's grout data sheet draws its line at 16°C (60°F) and 70% relative humidity, and asks for extended curing and protection past either. [MAPEI Ultracolor Plus FA] An unheated bathroom in winter, or one still steamy from a neighbouring shower, is on the wrong side of one of them.

Glass is the third. It is measured after the tile, so its wait cannot start early, and a tile job that runs late pushes the glass back with it.

Hidden damage found when the old board comes off, and a fixture moved after demolition, add repairs and plumbing under the membrane. To keep the schedule, treat the flood test as a gate, tile nothing until it passes, and book each inspection with the notice the Town asks for.

Can you use the bathroom during the renovation?

The shower is the last part of the room to come back. With cement-based grout, MAPEI's answer is 3 days minimum after the tile is installed before anyone showers. [MAPEI Ultracolor Plus FA] Grouting is not the end of the job either: the vanity, toilet and taps go in after the tile, so the toilet and sink stay out of service as well.

In a house with one bathroom, that is the stretch to plan around, and it ends when the grout has cured, not when the fixtures are connected.

Setting the order before a Sonce Homes bathroom starts

A Sonce Homes bathroom renovation starts behind the walls, with the plumbing and waterproofing done first. The trades back there, the exhaust fan vented outside among them, are coordinated so the room is opened once.

Send us a photo of the room as it is and tell us whether any fixture moves. That settles which of the waits above apply to your bathroom.

bathroom renovation

Keep reading

More from
the blog.

Your next project

Your home.
Your next chapter.

Tell us what you have in mind for your home, inside or out.

Request a quote

InsideGreat room

OutsidePergola & patio

Years in business
15+
Insured & licensed
WSIB
50 Google reviews
5.0★