Kitchens
How long does a kitchen renovation take? Living without a kitchen
Going without a sink or stove is the stretch you live through. What does set its length: the counter template after the cabinets, the ESA rough-in inspection and any permit review.
- Published
- Reading time
- 5 min read
- Written by
- Sonce Homes

The waits that decide your kitchen's schedule
How long a kitchen renovation takes depends less on demolition than on what the calendar waits for: the counter template, which only comes once the cabinets are in, the ESA rough-in inspection and, if a wall or the sink moves, a permit review. Settle the template date before you promise anyone a move-back date.
No official or manufacturer source puts a whole kitchen in weeks, so we give no total here. Scope decides how many of those waits apply. A refresh in the same layout often does without a building permit, so little stands between the design and the cabinet order. A full gut with a new layout can put a permit review ahead of demolition.
How long does a kitchen renovation take without a working sink?
You are without a kitchen from the day the old cabinets and counters come out until the new counter is set and the sink is connected to it. No source gives that stretch as a number of days. It is a chain, and each link waits on the one before: the rough-in and its inspection, the cabinets, the counter template, then the counter itself.
Two links depend on someone else's calendar. The walls stay open until ESA's inspector has seen the wiring, and the counter is cut by a fabricator who templates only once the room is ready. A late appliance or a second inspection visit lengthens the whole stretch, because the sink only comes back with the counter.
Plan it as a household. Before demolition, set up a cooking corner in another room near an outlet: a fridge, a kettle, a microwave. Wash up somewhere other than the kitchen sink, and use disposable plates if that saves carrying dishes. Ask your contractor when the water and power to the room will be shut off and when the sink is due back, and keep the template date in front of you, since the counter sets the end of the stretch.
Why the counters wait for the cabinets, and how long the gap is
A counter is cut from a template, and the template can be taken only once the room is ready for it. IKEA Canada's kitchen guide (the FY23 edition, written for its own custom countertops) says templating can be booked once the base cabinets are in with their doors, drawers and panels, levelled, and the appliances are in place, with the sink, faucet or cooktop on site. [IKEA Canada]
Caesarstone's guidance for fabricators, from October 2021, puts the line in nearly the same place: old countertop removed, all cabinetry fully installed and levelled, all appliances on site, plumbing and electrical done. [Caesarstone Canada] That list is why the counters trail the cabinets. The visit needs everything on it in place, and a missing item moves the visit.
The gap has two parts. Cabinets in to template is the one the list above governs. Template to install is the part no source times: neither page gives a number of days, so ask the fabricator for an install date when the template visit is booked.
When the ESA inspection falls, and what it holds up
Yes for new circuits, and the date that matters is the rough-in, because the walls stay open until it passes. Whoever does the electrical work files a notification with the Electrical Safety Authority (ESA) before the work starts, and that notification is separate from any building permit. [Electrical Safety Authority]
In a kitchen the rough-in comes once the layout is final, because the wiring is run to suit the cabinets and counters. The inspection happens after the circuits are wired and the boxes are set, and before anything buries them: insulation, vapour barrier, drywall. [Electrical Safety Authority] If the inspector finds defects, more than one rough-in inspection may be needed, and each repeat is another visit before the walls can close. [Electrical Safety Authority]
A job with a building permit has the Town's inspections too. East Gwillimbury says staff attend within 48 hours of a request, excluding weekends and holidays. [Town of East Gwillimbury] ESA's brochure gives no turnaround for its own visits, so ask the electrician when the rough-in inspection is booked.
Cabinet and appliance orders go in while the old kitchen still works
The job has four stages: planning and design, ordering, on-site construction and finishing. The first two happen while you still cook at home, and the layout has to be settled before anything is ordered, since custom cabinets are built to the plan.
Material and product availability is what stretches the timeline here, cabinets most of all, because the template, the counters and the backsplash all follow them. Their lead time varies by maker and is confirmed when the order is placed, and we found no published figure to plan on. Appliance delivery is the same, so ask for a date when you buy.
Choose the appliances and the sink in this stretch too. The fabricator templates around them, so they have to be on site before the stone is measured, and a delivery that lands late is a counter that lands late.
If a wall or the sink moves, the permit review comes first
Ontario's Building Code sets a 10-day timeframe for the approval or refusal of a building permit application for a house. [Government of Ontario] The page does not say whether those are working days. Newmarket publishes its own figure: about 10 to 15 working days to review an application once the form, fees and every submission requirement are in and deemed complete. [Town of Newmarket] East Gwillimbury's page gives no review window, so ask its building office.
The clock starts only when the application is complete. One that does not pass gets a deficiency letter listing what must be addressed before the permit can be issued. [Town of Newmarket] Moving walls, plumbing or the layout adds time because Newmarket counts adding or removing walls and plumbing alterations as permit work, which puts a review ahead of demolition. [Town of Newmarket] Our kitchen plans checklist goes through which kitchen work needs a permit.
The six-month start rule below is why an application should follow the cabinet order rather than lead it.
What pushes the finish date out after demolition
The first delay is a change made after the cabinet order. The layout is the decision everything else waits on: the cabinets are built to it, the counters are cut to the cabinets, and the plumbing and wiring are roughed in to suit both. Move the sink or an appliance late and the change runs down that chain to a new order and a later template visit.
The second is what demolition finds. The condition of a house behind its old cabinets and drywall is unknown until they come off, and in an older house repairs found in the walls add a step. A wall that comes out can have pipes, ducts and wiring inside it to reroute, so the wall is opened and checked before the plan is final.
The third is a failed rough-in. Each repeat inspection is one more visit the drywall waits for.
Getting a timeline for your kitchen from Sonce Homes
A schedule cannot be read off this page, because it turns on what only your kitchen can answer: whether the layout stays, which appliances and counter stone you choose, and what the walls hold once the old cabinets come off. Sonce Homes does kitchen renovation across layout, custom cabinetry and islands, quartz, granite and marble counters, a tile backsplash, floors and lighting.
Send us a photo of the kitchen as it is, a sketch or description of the one you want, and the date you hope to be cooking in it again. Say whether a wall or the sink moves.